revĂȘtements maibec sidings
quantites

Example - Area to cover : 1,000 sq ft.

EM+ AND REGULAR PROFILES : Contemporary, Rabbeted Bevel, Cove, V-Joint, Channel

To convert from sq ft to fbm

fbm = foot board measure
1 -
Area to cover x profile conversion factor
1" x 6" regular rabbeted bevel:
1.26 conversion factor
1,000 sq ft x 1.26 = 1,260 fbm
2 -
Add 3% for losses sue to cutting
Amount in fbm x 1.03
1,260 fbm x 1.03 = 1,298 fbm
Total amount : 1,298 fbm

To convert from sq ft to lin.ft.

lin.ft. = linear feet
1 -
Area to cover x profile conversion factor
1" x 6" regular rabbeted bevel:
2.52 conversion factor
1,000 sq ft x 2.52 = 2,520 lin.ft.
2 -
Add 3% for losses sue to cutting
Amount in lin.ft. x 1.03
2,520 lin.ft. x 1.03 = 2,596 lin.ft.
Total amount : 2,596 lin.ft.

BOARD AND BATTEN

To convert from sq ft to fbm

fbm = foot board measure
1 -
Area to cover x profile conversion factor
1,000 sq ft x 1.24 = 1,240 fbm


2 -
Add 3% for losses sue to cutting
Amount in fbm x 1.03
1,240 fbm x 1.03 = 1,277 fbm


Total amount : 1,277 fbm
3 -
To calculate the amount of 1" x 10" board
Multiply the total amount by 0.83
1,277 fbm x 0.83 = 1,060 fbm
4 -
To calculate the amount of 1" x 2" batten
Multiply the total amount by 0.17
Batten must be ordered in lin.ft.
Multiply the amount of fbm by 6
1,277 fbm x 0.17 = 217 fbm
217 fbm x 6 = 1,302 lin.ft.
Total amount to order :
1,060 fbm of board
and 1,302 lin.ft. of batten.

To convert from sq ft to lin.ft.

lin.ft. = linear feet
1 -
Divide sq ft by 9.25 and multiply by 12
 
1,000 sq ft / 9.25 x 12 = 1,298 lin.ft.
Same amount for board and batten
2 -
Add 3% for losses sue to cutting
Amount in lin.ft. x 1.03
1,298 lin.ft. x 1.03 = 1,337 lin.ft.
Same amount for board and batten
Total amount: 1,337 lin.ft.
 
1,337 lin.ft. of board

 
 
1,337 lin.ft of batten




Total amount to order :
1,337 lin.ft. of board
and 1,337 lin.ft. of batten
EM+ PROFILES Conversion Factors
sq ft - fbm sq ft - lin.ft.
Contemporary 1" x 6" 1.28 2.56
Rabbeted Bevel 1" x 6" 1.29 2.58
Cove 1" x 6" 1.27 2.54
V-Joint 1" x 6" 1.27 2.54
Channel 1" x 6" 1.27 2.54
REGULAR PROFILES Conversion Factors
sq ft - fbm sq ft - lin.ft.
Rabbeted Bevel


1" x 4"
1" x 6"
1" x 8"
1.45
1.26
1.23
4.35
2.52
1.85
Cove

1" x 6"
1" x 8"
1.26
1.23
2.52
1.85
V-Joint


1" x 4"
1" x 6"
1" x 8"
1.45
1.26
1.23
4.35
2.52
1.85
Channel

1" x 6"
1" x 8"
1.26
1.23
2.52
1.85
Board &
batten
1" x 10"

1" x 2"

1.24
Divide sq ft
by 9.25,
multiply by 12
THOR Conversion Factors
sq ft - fbm sq ft - lin.ft.
Rabbeted Bevel 1" x 6" 1.26 2.52

MOULDINGS

Add a minimum of 5% to the amount for losses due to cutting


SHINGLES

For 5" exposure, add 3% to the area to cover

1,000 ft2 x 1.03 = 1,030 ft2
1 box = 25 ft2
1,030 ft2 = 41 boxes
©2010 maibec inc. © All right reserved.
maibec